BATTERY STORAGE · ERCOT

Bluewind Energy Center

Bluewind Energy Center is a 103 MW battery storage request withdrawn in the ERCOT interconnection queue, in Atascosa County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2024 (completed)
  2. Withdrawn / abandonedApr 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
27INR0106
Grid region
ERCOT (Texas)
Developer
Bluewind Energy Center, LLC
Connection point (POI)
5713 Oaks Substation 138kV
Location
Atascosa County, Texas
Technology
Battery: 103 MW
Total requested
103 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
26 February 2024
Proposed online date
July 2026
Withdrawn
April 2025

Location

Marker shows the centre of Atascosa County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Atascosa County