SOLAR Β· ERCOT

Altita Solar

Altita Solar is a 182 MW solar request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2024 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
28INR0041
Grid region
ERCOT (Texas)
Developer
ACE DevCo NC, LLC
Connection point (POI)
138 kV Cotulla Substation (8610)
Technology
Solar: 182 MW
Total requested
182 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
7 February 2024
Proposed online date
May 2028

Location

No county location in the queue data.