πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Larimar Solar

Larimar Solar is a 151 MW solar request withdrawn in the ERCOT interconnection queue, in Bee County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2024 (completed)
  2. Withdrawn / abandonedApr 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
26INR0378
Grid region
ERCOT (Texas)
Developer
BT S7 Solar, LLC
Connection point (POI)
Tap 138 kV 8186 KENEDYSW4A β€šΓ„Γͺ 8590 TULETA4A
Location
Bee County, Texas
Technology
Solar: 151 MW
Total requested
151 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
10 January 2024
Proposed online date
December 2026
Withdrawn
April 2025

Location

Marker shows the centre of Bee County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Bee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem