United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTNightfall BESS SLF
Nightfall BESS SLF is a 11.0 MW battery storage request withdrawn in the ERCOT interconnection queue, in Uvalde County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2024 (completed)
- Withdrawn / abandonedJul 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 26INR0168
- Grid region
- ERCOT (Texas)
- Developer
- BDPU Solar Nightfall, LLC
- Connection point (POI)
- Tap 138KV 8707 Dryfrio - 8234 Uvalde
- Location
- Uvalde County, Texas
- Technology
- Battery: 11.0 MW
- Total requested
- 11.0 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 8 May 2024
- Proposed online date
- June 2026
- Withdrawn
- July 2025
Location
Marker shows the centre of Uvalde County; the queue data does not give exact sites.
Other requests in Uvalde County
- Nightfall SolarSolar · 181 MW · agreement signed
- Photo Solar 2Solar + storage · 300 MW · in study
- Photo BESS 2Solar + storage · 150 MW · in study
- Photo Solar 1Solar + storage · 150 MW · in study
- Photo BESS 3Solar + storage · 100 MW · in study
- Sunsetter BESSBattery storage · 100 MW · in study
- Photo BESS 1Solar + storage · 75.0 MW · in study
- Ashra Solar SLFSolar + storage · 40.3 MW · in study
- Ashra Storage SLFSolar + storage · 1.6 MW · in study
- Fluorite SolarSolar · 25.0 MW · suspended
- Basalt SolarSolar · 20.0 MW · suspended
- SunRaySolar · 204 MW · built