🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Mills Prairie Storage

Mills Prairie Storage is a 33.0 MW battery storage request withdrawn in the ERCOT interconnection queue, in Navarro County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2024 (completed)
  2. Withdrawn / abandonedJan 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
27INR0300
Grid region
ERCOT (Texas)
Developer
Mills Storage, LLC
Connection point (POI)
Tap 69kV #194 Purdon - #199 Brushie
Location
Navarro County, Texas
Technology
Battery: 33.0 MW
Total requested
33.0 MW
Study phase
FIS & SS Incomplete
Queue status
Withdrawn
Entered queue
18 November 2024
Proposed online date
August 2027
Withdrawn
January 2025

Location

Marker shows the centre of Navarro County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Navarro County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem