BATTERY STORAGE · ERCOT

Tierra Alta Storage SLF

Tierra Alta Storage SLF is a 205 MW battery storage request withdrawn in the ERCOT interconnection queue, in Schleicher County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2024 (completed)
  2. Withdrawn / abandonedApr 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
28INR0239
Grid region
ERCOT (Texas)
Developer
ET Fuels US Inc.
Connection point (POI)
Tap 138 kV 6490 Santiago – 6015 Maddux
Location
Schleicher County, Texas
Technology
Battery: 205 MW
Total requested
205 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
18 December 2024
Proposed online date
October 2028
Withdrawn
April 2025

Location

Marker shows the centre of Schleicher County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Schleicher County