🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in ERCOT (Texas) — page 19

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,158262.0 GW
Active in queue447.3 GW1,986 requests
Agreement signed119.3 GW578 requests
Withdrawn1,158262.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,158 requests · page 19 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Longfellow Ranch Partners Project Ph 1
Onshore wind · Riata Management, LLC
80.0 MWWithdrawn / abandoned ERCOT Sep 2008
Hill Solar
Solar · Sunchase Power
80.0 MWWithdrawn / abandoned Hill, TXERCOT Sep 2017target 2022
Inverter Field Storage
Other · CG WHARTON COUNTY LLC
80.0 MWWithdrawn / abandoned Wharton, TXERCOT Jan 2019target 2021
Ft. Stockton Solar
Solar · HelioSage
80.0 MWWithdrawn / abandoned ERCOT Dec 2013target 2016
Cameron Wind
Onshore wind · Cielo Wind Power
80.0 MWWithdrawn / abandoned ERCOT Sep 2001target 2050
Grian Solar
Solar · Lightsource Renewable Energy Development, LLC
80.0 MWWithdrawn / abandoned Ellis, TXERCOT Dec 2019target 2021
Lindsay Solar
Solar · HelioSage
80.0 MWWithdrawn / abandoned ERCOT Dec 2013target 2017
Cannon Solar SLF
Solar · Cannon Solar, LLC
80.0 MWWithdrawn / abandoned ERCOT Sep 2020target 2027
Merrifield Solar
Solar · Belltown Power
80.0 MWWithdrawn / abandoned Hill, TXERCOT Jun 2018target 2020
Magic Valley Chillers
Gas · Calpine
79.0 MWWithdrawn / abandoned ERCOT Nov 2012target 2016
Palmas Altas Wind
Onshore wind · Cielo Wind Services
78.0 MWWithdrawn / abandoned ERCOT May 2009target 2050
Nereida Solar
Solar · ABEI & INFRASTRUCTURE S.L.
77.6 MWWithdrawn / abandoned Jones, TXERCOT May 2019target 2022
Augustus Solar
Solar · Industrial Golf Project LLC
76.7 MWWithdrawn / abandoned Martin, TXERCOT Jan 2023target 2026
Barrett Storage
Other · BT Barrett Solar, LLC
76.5 MWWithdrawn / abandoned Rains, TXERCOT Dec 2022target 2024
BRP Galan BESS
Battery storage · BRP Galan BESS LLC
76.0 MWWithdrawn / abandoned ERCOT Aug 2020target 2027
SBranch Expansion Solar
Solar · CG Wharton County LLC
76.0 MWWithdrawn / abandoned Wharton, TXERCOT Oct 2020target 2022
Homestead BESS
Other · Homestead Power LLC
75.8 MWWithdrawn / abandoned Bell, TXERCOT Mar 2023target 2024
Claxton Storage
Battery storage · BT Claxton Solar, LLC
75.7 MWWithdrawn / abandoned ERCOT Sep 2022target 2027
Burkburnett Solar
Solar · Sunchase Power
75.0 MWWithdrawn / abandoned ERCOT Nov 2016target 2018
Callahan Wind Farm
Onshore wind · RES North America
75.0 MWWithdrawn / abandoned ERCOT Dec 2002target 2050
Saltgrass-Sargent Wind
Onshore wind · Duke Energy Generation Services
75.0 MWWithdrawn / abandoned ERCOT Oct 2008target 2050
TX_Marfa_Solar
Solar · Lincoln Renewable Energy, LLC
75.0 MWWithdrawn / abandoned ERCOT Oct 2012target 2015
Millhouse Solar
Solar · Cypress Creek Renewables
75.0 MWWithdrawn / abandoned Jim Wells, TXERCOT Nov 2017target 2020
McGee Storage 2
Other · BT McGee Storage, LLC
74.9 MWWithdrawn / abandoned Henderson, TXERCOT target 2026
Kirkwall Solar
Solar · ABEI ENERGY
73.1 MWWithdrawn / abandoned Williamson, TXERCOT Nov 2020target 2023
Gold Coin Storage
Battery storage · Grenergy USA
73.0 MWWithdrawn / abandoned ERCOT Nov 2024target 2027
PV New Glory
Solar · PREMIER ENGINEERING USA CORP.
72.5 MWWithdrawn / abandoned Stonewall, TXERCOT Oct 2021target 2024
Blue Star Solar
Solar · GH America Energy, LLC
72.3 MWWithdrawn / abandoned Val Verde, TXERCOT Nov 2021target 2024
Country Haven Energy Storage
Battery storage · 174 Power Global Properties, LLC
72.1 MWWithdrawn / abandoned ERCOT Mar 2023target 2026
Windwood Project
Onshore wind · Lincoln Renewable Energy, LLC
72.0 MWWithdrawn / abandoned ERCOT Jan 2010target 2014
Stillwater Storage
Other · Cypress Creek Renewables
72.0 MWWithdrawn / abandoned Nueces, TXERCOT Nov 2017target 2020
High Chap Storage
Battery storage · HIGH CHAPARRAL SOLAR PROJECT LLC
71.8 MWWithdrawn / abandoned Brazoria, TXERCOT Jul 2022target 2028
Limestone Wind Farm
Onshore wind · Pioneer Green Energy, LLC
71.0 MWWithdrawn / abandoned ERCOT Oct 2011target 2013
Big Wind
Onshore wind · Your Resources, LLC
70.0 MWWithdrawn / abandoned ERCOT Apr 2008target 2050
Delaware Mt Solar
Solar · Nextera
70.0 MWWithdrawn / abandoned ERCOT Nov 2013target 2016
Blue Summit Windfarm ph 2
Onshore wind · FPL Energy, LLC
70.0 MWWithdrawn / abandoned ERCOT Apr 2008
Hathor Solar
Solar · ABEI ENERGY & INFRASTRUCTURE
67.6 MWWithdrawn / abandoned Hunt, TXERCOT Sep 2020target 2023
Temple Generation I Repower
Gas
67.0 MWWithdrawn / abandoned Bell, TXERCOT Apr 2021
Pioneer Hutt Solar (Add Additional MWs)
Solar · Pioneer Hutt Solar, LLC
65.8 MWWithdrawn / abandoned Midland, TXERCOT target 2025
Blue Sky Solar
Solar · Blue Sky Solar
65.0 MWWithdrawn / abandoned Crockett, TXERCOT Feb 2020target 2022
Cargil Solar
Solar · Cypress Creek Renewables
65.0 MWWithdrawn / abandoned ERCOT Nov 2017target 2020
BRP Avila II BESS
Other · BRP Avila BESS LLC
63.7 MWWithdrawn / abandoned Pecos, TXERCOT Oct 2021target 2023
Sun Cactus Storage
Other · Sun Cactus Solar Project, LLC
63.2 MWWithdrawn / abandoned Duval, TXERCOT Jul 2022target 2026
Nezuko BESS
Battery storage · AEU BATTERY PROJECT I LLC
63.1 MWWithdrawn / abandoned ERCOT Jul 2023target 2028
Mason Mt Wind
Onshore wind · Enel Green
62.0 MWWithdrawn / abandoned ERCOT Apr 2014target 2019
Enbridge Ingleside Storage Cancel
Other · Enbridge Ingleside Solar, LLC
61.9 MWWithdrawn / abandoned San Patricio, TXERCOT target 2025
Enbridge Ingleside Solar Cancel
Solar · Enbridge Ingleside Solar, LLC
61.9 MWWithdrawn / abandoned San Patricio, TXERCOT target 2025
Enbridge Ingleside Solar SLF
Solar · Enbridge Ingleside Solar, LLC
61.9 MWWithdrawn / abandoned San Patricio, TXERCOT Aug 2022target 2025
OCI SunRoper MW Increase to 24INR0167
Solar · OCI SunRoper LLC
61.6 MWWithdrawn / abandoned Wharton, TXERCOT target 2025
Langer Storage
Battery storage · Langer Solar, LLC
61.5 MWWithdrawn / abandoned Bosque, TXERCOT May 2021target 2027
Page 19 of 24

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)