United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTPioneer Hutt Solar (Add Additional MWs)
Pioneer Hutt Solar (Add Additional MWs) is a 65.8 MW solar request withdrawn in the ERCOT interconnection queue, in Midland County, Texas.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandonedOct 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 25INR0508
- Grid region
- ERCOT (Texas)
- Developer
- Pioneer Hutt Solar, LLC
- Connection point (POI)
- #23863 Driver Station 138kV
- Location
- Midland County, Texas
- Technology
- Solar: 65.8 MW
- Total requested
- 65.8 MW
- Study phase
- FIS & SS Incomplete
- Queue status
- Withdrawn
- Proposed online date
- August 2025
- Withdrawn
- October 2023
Location
Marker shows the centre of Midland County; the queue data does not give exact sites.
Other requests in Midland County
- Greater Bryant G SolarSolar · 17.7 MW · agreement signed
- TRIFECTA GasGas · 453 MW · in study
- Energy City BESSBattery storage · 205 MW · in study
- Drill Baby Drill BESSBattery storage · 204 MW · in study
- Jasper BESSBattery storage · 201 MW · in study
- Pioneer Hutt Solar (Alternative POI)Solar · 116 MW · in study
- Pioneer Hutt SolarSolar · 116 MW · suspended
- Pioneer DJ WindOnshore wind · 140 MW · built
- Gas project GEN-2009-007, Midland CountyGas · 550 MW · withdrawn
- Hutt WindOnshore wind · 336 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem