United States βΊ Grid βΊ Interconnection queues βΊ Texas
GAS Β· SPPGas project GEN-2009-007, Midland County
Gas project GEN-2009-007, Midland County is a 550 MW gas request withdrawn in the SPP interconnection queue, in Midland County, Texas, connecting to SPS.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2009 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2009-007
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Midland 345kV
- Location
- Midland County, Texas
- Technology
- Gas: 550 MW
- Total requested
- 550 MW
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 20 February 2009
- Proposed online date
- January 2012
Location
Marker shows the centre of Midland County; the queue data does not give exact sites.
Other requests in Midland County
- Greater Bryant G SolarSolar Β· 17.7 MW Β· agreement signed
- TRIFECTA GasGas Β· 453 MW Β· in study
- Energy City BESSBattery storage Β· 205 MW Β· in study
- Drill Baby Drill BESSBattery storage Β· 204 MW Β· in study
- Jasper BESSBattery storage Β· 201 MW Β· in study
- Pioneer Hutt Solar (Alternative POI)Solar Β· 116 MW Β· in study
- Pioneer Hutt SolarSolar Β· 116 MW Β· suspended
- Pioneer DJ WindOnshore wind Β· 140 MW Β· built
- Hutt WindOnshore wind Β· 336 MW Β· withdrawn
- Pioneer Hutt Solar (Add Additional MWs)Solar Β· 65.8 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem