United States βΊ Grid βΊ Interconnection queues βΊ Texas
GAS Β· ERCOTTRIFECTA Gas
TRIFECTA Gas is a 453 MW gas request in interconnection study in the ERCOT interconnection queue, in Midland County, Texas.
Queue statusIn planning
- PlanningQueued Jun 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Feb 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 26INR0183
- Grid region
- ERCOT (Texas)
- Developer
- NET Power
- Connection point (POI)
- Tap 345 kV 1185 Midland County Northwest Switch (bus #1185) βΓΓ¬ Midland East (bus #1021) 345 kV Line Ckt 01
- Location
- Midland County, Texas
- Technology
- Gas: 453 MW
- Total requested
- 453 MW
- Study phase
- SS Completed, FIS Completed, No IA
- Queue status
- Active
- Entered queue
- 28 June 2023
- Proposed online date
- February 2030
Location
Marker shows the centre of Midland County; the queue data does not give exact sites.
Other requests in Midland County
- Greater Bryant G SolarSolar Β· 17.7 MW Β· agreement signed
- Energy City BESSBattery storage Β· 205 MW Β· in study
- Drill Baby Drill BESSBattery storage Β· 204 MW Β· in study
- Jasper BESSBattery storage Β· 201 MW Β· in study
- Pioneer Hutt Solar (Alternative POI)Solar Β· 116 MW Β· in study
- Pioneer Hutt SolarSolar Β· 116 MW Β· suspended
- Pioneer DJ WindOnshore wind Β· 140 MW Β· built
- Gas project GEN-2009-007, Midland CountyGas Β· 550 MW Β· withdrawn
- Hutt WindOnshore wind Β· 336 MW Β· withdrawn
- Pioneer Hutt Solar (Add Additional MWs)Solar Β· 65.8 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem