United States βΊ Grid βΊ Interconnection queues βΊ Texas
ONSHORE WIND Β· ERCOTHutt Wind
Hutt Wind is a 336 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Midland County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2017 (completed)
- Withdrawn / abandonedMar 2022 (project stopped here)
- ConsentedMay 2020 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 21INR0005
- Grid region
- ERCOT (Texas)
- Developer
- Pioneer Natural Resources
- Connection point (POI)
- tap 345kV 11028 Odessa - 59901 Grelton
- Location
- Midland County, Texas
- Technology
- Wind: 336 MW
- Total requested
- 336 MW
- Study phase
- IA and FIS Pending
- Queue status
- Withdrawn
- Entered queue
- 5 September 2017
- Agreement signed
- 26 May 2020
- Proposed online date
- April 2023
- Withdrawn
- March 2022
Location
Marker shows the centre of Midland County; the queue data does not give exact sites.
Other requests in Midland County
- Greater Bryant G SolarSolar Β· 17.7 MW Β· agreement signed
- TRIFECTA GasGas Β· 453 MW Β· in study
- Energy City BESSBattery storage Β· 205 MW Β· in study
- Drill Baby Drill BESSBattery storage Β· 204 MW Β· in study
- Jasper BESSBattery storage Β· 201 MW Β· in study
- Pioneer Hutt Solar (Alternative POI)Solar Β· 116 MW Β· in study
- Pioneer Hutt SolarSolar Β· 116 MW Β· suspended
- Pioneer DJ WindOnshore wind Β· 140 MW Β· built
- Gas project GEN-2009-007, Midland CountyGas Β· 550 MW Β· withdrawn
- Pioneer Hutt Solar (Add Additional MWs)Solar Β· 65.8 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem