SOLAR Β· ERCOT

Hill Solar

Hill Solar is a 80.0 MW solar request withdrawn in the ERCOT interconnection queue, in Hill County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2017 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
19INR0135
Grid region
ERCOT (Texas)
Developer
Sunchase Power
Connection point (POI)
tap 69kV 3523 Hillsboro - 3532 Itasca
Location
Hill County, Texas
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
21 September 2017
Proposed online date
December 2022
Withdrawn
March 2023

Location

Marker shows the centre of Hill County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Hill County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem