ONSHORE WIND · ERCOT

Aquilla Lake 3 Wind

Aquilla Lake 3 Wind is a 297 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Hill County, Texas.

Queue statusConsented
  1. PlanningQueued Mar 2021 (completed)
  2. ConsentedJan 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0499
Grid region
ERCOT (Texas)
Developer
Aquilla Lake 3 Wind
Connection point (POI)
tap 345 kV 68040 Kopperl to 68091 Navarro
Location
Hill County, Texas
Technology
Wind: 297 MW
Total requested
297 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
8 March 2021
Agreement signed
24 January 2024
Proposed online date
March 2027

Location

Marker shows the centre of Hill County; the queue data does not give exact sites.