πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

GAS Β· ERCOT

Magic Valley Chillers

Magic Valley Chillers is a 79.0 MW gas request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2012 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
15INR0027
Grid region
ERCOT (Texas)
Developer
Calpine
Technology
Gas: 79.0 MW
Total requested
79.0 MW
Study phase
FIS Complete
Queue status
Withdrawn
Entered queue
14 November 2012
Proposed online date
June 2016

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem