ONSHORE WIND Β· ERCOT

Blue Summit Windfarm ph 2

Blue Summit Windfarm ph 2 is a 70.0 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
07INR0014b
Grid region
ERCOT (Texas)
Developer
FPL Energy, LLC
Technology
Wind: 70.0 MW
Total requested
70.0 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
1 April 2008

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem