United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in ISO-NE (New England) — page 13
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Solar Solar |
19.9 MW | Withdrawn / abandoned |
| Solar Solar |
19.9 MW | Withdrawn / abandoned |
| Tilton Heights Energy Center Solar |
19.9 MW | Withdrawn / abandoned |
| Keay Brook Energy Solar Solar |
19.9 MW | Withdrawn / abandoned |
| Black Hill Point Energy Center Solar |
19.9 MW | Withdrawn / abandoned |
| Solar Solar |
19.9 MW | Withdrawn / abandoned |
| Solar Solar |
19.9 MW | Withdrawn / abandoned |
| Solar Solar |
19.9 MW | Withdrawn / abandoned |
| Solar Solar |
19.9 MW | Withdrawn / abandoned |
| Solar Solar |
19.9 MW | Withdrawn / abandoned |
| Solar Solar |
19.9 MW | Withdrawn / abandoned |
| Solar Solar |
19.9 MW | Withdrawn / abandoned |
| Solar Solar |
19.8 MW | Withdrawn / abandoned |
| Solar Solar |
19.8 MW | Withdrawn / abandoned |
| Wind Onshore wind |
19.8 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
19.7 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
19.7 MW | Withdrawn / abandoned |
| Solar Solar |
19.6 MW | Withdrawn / abandoned |
| Saco Solar Solar |
19.6 MW | Withdrawn / abandoned |
| Wind Onshore wind |
19.5 MW | Withdrawn / abandoned |
| Eversource Group @ Wing Lane 624 Solar + storage |
19.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
19.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
18.9 MW | Withdrawn / abandoned |
| Enfield DG Cluster Solar + storage |
18.8 MW | Withdrawn / abandoned |
| CMP Winslow 115 kV SS - Winslow-Lakewood Areas Study Solar + storage |
18.7 MW | Withdrawn / abandoned |
| Augusta E/Puddledock/Bowman St 115 kV SS - Midcoast Area DG Study Solar + storage |
18.6 MW | Withdrawn / abandoned |
| Group @ Hatchville 936 - EMA ASO Solar + storage |
18.5 MW | Withdrawn / abandoned |
| Solar Solar |
18.4 MW | Withdrawn / abandoned |
| Gas Turbine Capacity Increase ( See queue position Gas |
18.4 MW | Withdrawn / abandoned |
| Palmer Substation - NG Western MA Area Cluster Study Solar |
18.1 MW | Withdrawn / abandoned |
| Biomass Other |
18.1 MW | Withdrawn / abandoned |
| Bridgeport Energy Wet Compression Upgrade Gas |
18.0 MW | Withdrawn / abandoned |
| Wind Onshore wind |
18.0 MW | Withdrawn / abandoned |
| Mirant Kendall Jet 2 Other |
18.0 MW | Withdrawn / abandoned |
| Wind Onshore wind |
18.0 MW | Withdrawn / abandoned |
| Pembroke Solar Solar |
17.5 MW | Withdrawn / abandoned |
| Group @ Medway 65 - EMA ASO Solar + storage |
17.5 MW | Withdrawn / abandoned |
| wind Onshore wind |
17.4 MW | Withdrawn / abandoned |
| Solar Solar |
17.2 MW | Withdrawn / abandoned |
| Solar Solar |
17.0 MW | Withdrawn / abandoned |
| W. Charlton substation - NG Western MA Area Cluster Study Solar |
17.0 MW | Withdrawn / abandoned |
| EE 2024 SEMA/Cape ASO Group Study Solar + storage |
16.9 MW | Withdrawn / abandoned |
| Group @ Industrial Park 636 - EMA ASO Solar + storage |
16.5 MW | Withdrawn / abandoned |
| Kendall Combined Cycle increase Gas |
16.4 MW | Withdrawn / abandoned |
| Wind Onshore wind |
16.1 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)