Bridgeport Energy Wet Compression Upgrade

Bridgeport Energy Wet Compression Upgrade is a 18.0 MW gas request withdrawn in the ISO-NE interconnection queue, in Fairfield County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2015 (completed)
  2. Withdrawn / abandonedSep 2017 (project stopped here)
  3. ConsentedApr 2016 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
530
Grid region
ISO-NE (New England)
Connection point (POI)
UI Singer Substation
Location
Fairfield County, Connecticut
Technology
Gas: 18.0 MW
Total requested
18.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Withdrawn
Entered queue
26 February 2015
Agreement signed
13 April 2016
Proposed online date
June 2018
Withdrawn
September 2017

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in Fairfield County