GAS · ISO-NE

Combined Cycle Upgrade

Combined Cycle Upgrade is a 4.0 MW gas request built and operating in the ISO-NE interconnection queue, in Fairfield County, Connecticut.

Queue statusOperating
  1. PlanningQueued Mar 2020 (completed)
  2. ConsentedJul 2021 (completed)
  3. Construction (completed)
  4. OperatingTarget Jul 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
971
Grid region
ISO-NE (New England)
Connection point (POI)
UI Singer Substation
Location
Fairfield County, Connecticut
Technology
Gas: 4.0 MW
Total requested
4.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
26 March 2020
Agreement signed
12 July 2021
Proposed online date
July 2021

Location

No county location in the queue data.