SOLAR Β· ISO-NE

Solar

Solar is a 20.0 MW solar request withdrawn in the ISO-NE interconnection queue, in New Haven County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2017 (completed)
  2. Withdrawn / abandonedMay 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
629
Grid region
ISO-NE (New England)
Connection point (POI)
CT_NU 115 kV Line from Wallingford to NU_1208_WAL. Proposed POI is located at 41° 26β€šΓ„Γ΄ 27.9β€šΓ„ΓΉ N , 72° 50β€šΓ„Γ΄36.6β€šΓ„ΓΉ W (see the drawing with file name "Project Facility Layout - 22NOV16.pdf" for a
Location
New Haven County, Connecticut
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
7 March 2017
Proposed online date
December 2018
Withdrawn
May 2017

Location

No county location in the queue data.