United States › Grid › Interconnection queues › Connecticut
SOLAR · ISO-NEBlack Hill Point Energy Center
Black Hill Point Energy Center is a 19.9 MW solar request withdrawn in the ISO-NE interconnection queue, in Windham County, Connecticut.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2018 (completed)
- Withdrawn / abandonedNov 2024 (project stopped here)
- ConsentedApr 2022 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 787
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- New 3 breaker ring bus switching station on Eversource (CL&P) Killingly to Tunnel 115 kV line L-1607.
- Location
- Windham County, Connecticut
- Technology
- Solar: 19.9 MW
- Total requested
- 19.9 MW
- Service type
- Energy only (ERIS)
- Study phase
- Executed
- Queue status
- Withdrawn
- Entered queue
- 26 September 2018
- Agreement signed
- 12 April 2022
- Proposed online date
- September 2025
- Withdrawn
- November 2024
Location
No county location in the queue data.
Power plants in Connecticut · Transmission lines in Connecticut
Other requests in Windham County
- Husky SolarSolar · 50.2 MW · agreement signed
- Lake Road UpgradesGas · 49.8 MW · built
- Quinebaug SolarSolar · 49.0 MW · built
- Plainfield Renewable Energy ProjectOther · 37.5 MW · built
- Mechanicsville Hydro IncreaseHydro · 0.3 MW · built
- Combined CycleGas · 1,120 MW · withdrawn
- NTE ConnecticutGas · 672 MW · withdrawn
- Combined CycleGas · 563 MW · withdrawn
- Battery StorageBattery storage · 325 MW · withdrawn
- Battery StorageBattery storage · 300 MW · withdrawn
- Combined CycleGas · 250 MW · withdrawn
- Battery StorageBattery storage · 205 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem