πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Maine

SOLAR Β· ISO-NE

Solar

Solar is a 19.6 MW solar request withdrawn in the ISO-NE interconnection queue, in Penobscot County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2024 (completed)
  2. Withdrawn / abandonedSep 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1547
Grid region
ISO-NE (New England)
Connection point (POI)
Clifton Switchyard in Clifton, Maine.
Location
Penobscot County, Maine
Technology
Solar: 19.6 MW
Total requested
19.6 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
31 May 2024
Proposed online date
December 2027
Withdrawn
September 2025

Location

Marker shows the centre of Penobscot County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in Penobscot County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem