Pisgah Mountain

Pisgah Mountain is a 9.0 MW onshore wind request built and operating in the ISO-NE interconnection queue, in Penobscot County, Maine.

Queue statusOperating
  1. PlanningQueued Oct 2010 (completed)
  2. ConsentedOct 2012 (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
349
Grid region
ISO-NE (New England)
Connection point (POI)
BHE Line 66
Location
Penobscot County, Maine
Technology
Wind: 9.0 MW
Total requested
9.0 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Operational
Entered queue
20 October 2010
Agreement signed
24 October 2012
Proposed online date
December 2016

Location

Marker shows the centre of Penobscot County; the queue data does not give exact sites.

Power plants in Maine · Transmission lines in Maine