BATTERY STORAGE · ISO-NEBattery Storage
Battery Storage is a 20.0 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Hartford County, Connecticut.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2018 (completed)
- Withdrawn / abandonedMay 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 717
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Eversource North Bloomfield 2A
- Location
- Hartford County, Connecticut
- Technology
- Battery: 20.0 MW
- Total requested
- 20.0 MW
- Queue status
- Withdrawn
- Entered queue
- 21 February 2018
- Proposed online date
- February 2022
- Withdrawn
- May 2022
Location
No county location in the queue data.
Power plants in Connecticut · Transmission lines in Connecticut
Other requests in Hartford County
- SolarSolar · 150 MW · agreement signed
- Broadleaf SolarSolar · 101 MW · agreement signed
- SolarSolar · 25.0 MW · in study
- Solar IncreaseSolar · 5.0 MW · in study
- Gravel Pit SolarSolar · 50.0 MW · built
- Algonquin Power Windsor Locks Cogeneration FacilitGas · 47.5 MW · built
- Gravel Pit Solar IncreaseSolar · 45.0 MW · built
- SolarSolar · 26.4 MW · built
- Gravel Pit Solar increaseSolar · 25.0 MW · built
- NB Fuel CellGas · 20.2 MW · built
- Nutmeg Solar, LLCSolar · 19.9 MW · built
- Hamilton SundstrandGas · 5.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem