BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 20.0 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Hartford County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2018 (completed)
  2. Withdrawn / abandonedMay 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
717
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource North Bloomfield 2A
Location
Hartford County, Connecticut
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Queue status
Withdrawn
Entered queue
21 February 2018
Proposed online date
February 2022
Withdrawn
May 2022

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in Hartford County