Battery Storage is a 19.7 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Worcester County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2024 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1571
Grid region
ISO-NE (New England)
Connection point (POI)
42.066328, -71.864144 National Grid 69 kV Substation the East Webster 412 substation.
Location
Worcester County, Massachusetts
Technology
Battery: 19.7 MW
Total requested
19.7 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
13 June 2024
Proposed online date
June 2027
Withdrawn
October 2025

Location

Marker shows the centre of Worcester County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Worcester County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem