United States › Grid › Interconnection queues › Massachusetts
SOLAR · ISO-NEHarrington Street PV Project (QF)
Harrington Street PV Project (QF) is a 9.8 MW solar request built and operating in the ISO-NE interconnection queue, in Worcester County, Massachusetts, connecting to NGRID.
Request details
- Queue ID
- 377
- Grid region
- ISO-NE (New England)
- Utility / transmission owner
- NGRID
- Connection point (POI)
- GRID 69 kV
- Location
- Worcester County, Massachusetts
- Technology
- Solar: 9.8 MW
- Total requested
- 9.8 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 14 September 2011
- Proposed online date
- December 2016
Location
Marker shows the centre of Worcester County; the queue data does not give exact sites.
Power plants in Massachusetts · Transmission lines in Massachusetts
Other requests in Worcester County
- Battery StorageBattery storage · 204 MW · agreement signed
- Battery StorageBattery storage · 300 MW · in study
- Battery StorageBattery storage · 180 MW · in study
- Combined Cycle Uprate #2Gas · 30.0 MW · built
- Crystal Lake Substation - NG Western MA Area Cluster StudySolar · 24.7 MW · built
- Solar with BatterySolar + storage · 10.0 MW · built
- Litchfield substation - NG Western MA Area Cluster StudySolar · 9.5 MW · built
- N. Oxford Substation - NG Western MA Area Cluster StudySolar · 8.7 MW · built
- SolarSolar · 8.0 MW · built
- Fitchburg Renewable EnergyOther · 7.2 MW · built
- SolarSolar · 6.0 MW · built
- Westminster - NG Western MA Area Cluster StudySolar · 4.9 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem