United States βΊ Grid βΊ Interconnection queues βΊ New Hampshire
SOLAR Β· ISO-NESolar
Solar is a 20.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Cheshire County, New Hampshire.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2024 (completed)
- Withdrawn / abandonedAug 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1576
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Eversource 115kV Section L-163, approximately 2.6 miles north of North Keene Substation.
- Location
- Cheshire County, New Hampshire
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 26 June 2024
- Proposed online date
- June 2028
- Withdrawn
- August 2024
Location
Marker shows the centre of Cheshire County; the queue data does not give exact sites.
Power plants in New Hampshire Β· Transmission lines in New Hampshire
Other requests in Cheshire County
- Energy CenterGas Β· 570 MW Β· withdrawn
- Solar plus BatterySolar + storage Β· 102 MW Β· withdrawn
- SolarSolar Β· 98.0 MW Β· withdrawn
- SolarSolar Β· 78.4 MW Β· withdrawn
- SolarSolar Β· 65.0 MW Β· withdrawn
- Chariot SolarSolar Β· 49.5 MW Β· withdrawn
- BiomassOther Β· 40.0 MW Β· withdrawn
- SolarSolar Β· 30.0 MW Β· withdrawn
- SolarSolar Β· 30.0 MW Β· withdrawn
- BiomassOther Β· 20.0 MW Β· withdrawn
- Biomass ProjectOther Β· 20.0 MW Β· withdrawn
- SolarSolar Β· 14.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem