🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Hampshire

SOLAR + STORAGE · ISO-NE

Solar plus Battery

Solar plus Battery is a 102 MW solar + storage request withdrawn in the ISO-NE interconnection queue, in Cheshire County, New Hampshire.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedAug 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1316
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource 115kV line L163
Location
Cheshire County, New Hampshire
Technology
Solar: 102 MW · Battery
Total requested
102 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
30 September 2022
Proposed online date
October 2027
Withdrawn
August 2023

Location

Marker shows the centre of Cheshire County; the queue data does not give exact sites.

Power plants in New Hampshire · Transmission lines in New Hampshire

Other requests in Cheshire County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem