πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Hampshire

OTHER Β· ISO-NE

Biomass

Biomass is a 40.0 MW other request withdrawn in the ISO-NE interconnection queue, in Cheshire County, New Hampshire.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2004 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
126
Grid region
ISO-NE (New England)
Connection point (POI)
N-186, 115kV line between Vernon Road Tap and bor
Location
Cheshire County, New Hampshire
Technology
Other: 40.0 MW
Total requested
40.0 MW
Service type
Other
Queue status
Withdrawn
Entered queue
9 November 2004
Proposed online date
July 2007

Location

Marker shows the centre of Cheshire County; the queue data does not give exact sites.

Power plants in New Hampshire Β· Transmission lines in New Hampshire

Other requests in Cheshire County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem