πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Hampshire

GAS Β· ISO-NE

Energy Center

Energy Center is a 570 MW gas request withdrawn in the ISO-NE interconnection queue, in Cheshire County, New Hampshire.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2015 (completed)
  2. Withdrawn / abandonedApr 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
579
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource (PSNH) 379 line crossing Forest Lake Road (POI will be south of Forest Lake Road), which is in close proximity to the Project site.
Location
Cheshire County, New Hampshire
Technology
Gas: 570 MW Β· Other
Total requested
570 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
25 November 2015
Proposed online date
June 2020
Withdrawn
April 2016

Location

Marker shows the centre of Cheshire County; the queue data does not give exact sites.

Power plants in New Hampshire Β· Transmission lines in New Hampshire

Other requests in Cheshire County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem