πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Hampshire

OTHER Β· ISO-NE

Biomass

Biomass is a 20.0 MW other request withdrawn in the ISO-NE interconnection queue, in Cheshire County, New Hampshire.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2009 (completed)
  2. Withdrawn / abandonedOct 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
312
Grid region
ISO-NE (New England)
Connection point (POI)
PSNH 34.5 kV to Winchester substation
Location
Cheshire County, New Hampshire
Technology
Other: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
18 September 2009
Proposed online date
October 2013
Withdrawn
October 2011

Location

Marker shows the centre of Cheshire County; the queue data does not give exact sites.

Power plants in New Hampshire Β· Transmission lines in New Hampshire

Other requests in Cheshire County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem