United States › Grid › Interconnection queues › Texas
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in Texas, ERCOT
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Corner Solar Solar · Shannon Solar LLC |
1,222 MW | Withdrawn / abandoned |
| R-Cube Wind Onshore wind · Nextera |
1,000 MW | Withdrawn / abandoned |
| FGE Texas 1 Gas Gas · FGE Power |
743 MW | Withdrawn / abandoned |
| Greens Bayou 9 CCGT Gas · NRG Texas Power LLC |
721 MW | Withdrawn / abandoned |
| Tehuacana Creek Solar-Alt POI Solar · Tehuacana Creek Solar LLC |
715 MW | Withdrawn / abandoned |
| Hollow Branch Creek Solar SLF Solar · Hollow Branch Creek Solar LLC |
712 MW | Withdrawn / abandoned |
| Goldenrod Creek Solar Solar · Goldenrod Creek Solar LLC |
660 MW | Withdrawn / abandoned |
| Bastrop Peaking Generators II Gas · MPH Bastrop Peakers, LLC |
628 MW | Withdrawn / abandoned |
| Cosmos Solar Solar · EDF Renewables Development, Inc. |
610 MW | Withdrawn / abandoned |
| Old Lunar Solar Solar · EDF Renewables Development, Inc. |
610 MW | Withdrawn / abandoned |
| Scandia Wind DEF Onshore wind · Scandia Wind LLC |
600 MW | Withdrawn / abandoned |
| Apis Solar Solar · S&S Renewables LLC |
534 MW | Withdrawn / abandoned |
| Dundee East A Wind Placeholder Onshore wind · Felix 2, LLC |
524 MW | Withdrawn / abandoned |
| OFFERED Combined Cycle Gen Gas · Blue Cube Operations |
520 MW | Withdrawn / abandoned |
| Bronze Fork Solar Solar · EDF Renewables Development, Inc. |
516 MW | Withdrawn / abandoned |
| Point Mountain Solar Solar · Hecate Energy |
514 MW | Withdrawn / abandoned |
| Point Mountain Solar Solar · Hecate Energy Point Mountain LLC |
514 MW | Withdrawn / abandoned |
| Brinton Fork Solar Solar · EDF Renewables Development, Inc. |
514 MW | Withdrawn / abandoned |
| Amsterdam Solar II Solar · Cottonwood Bayou Solar II, LLC |
510 MW | Withdrawn / abandoned |
| Shinnery Hill Solar Solar · EDF Renewables Development, Inc. |
503 MW | Withdrawn / abandoned |
| Green Bird Solar Solar · Gigawatt Solar LLC |
502 MW | Withdrawn / abandoned |
| Dark Lark BESS Other |
500 MW | Withdrawn / abandoned |
| Green Valley Wind Onshore wind · Eon |
500 MW | Withdrawn / abandoned |
| Comanche Run Wind Onshore wind · Avangrid |
500 MW | Withdrawn / abandoned |
| Juno Storage Other · Intersect Power |
495 MW | Withdrawn / abandoned |
| ELTEX Power Station Gas · ELTEX Power Station LLC |
488 MW | Withdrawn / abandoned |
| Sugarland Power Plant Gas · ProEnergy Services LLC |
484 MW | Withdrawn / abandoned |
| Halyard Henderson Gas · Halyard Energy |
484 MW | Withdrawn / abandoned |
| Ponta Power Plant Gas · Pro Energy Services LLC |
484 MW | Withdrawn / abandoned |
| Denver City - Mustang - Gas Gas · Golden Spread Electric Cooperative, Inc. |
472 MW | Withdrawn / abandoned |
| Deepwater Gas · AES |
462 MW | Withdrawn / abandoned |
| Upstream BESS Battery storage · Upstream Storage LLC |
462 MW | Withdrawn / abandoned |
| Ponta Power Station Gas · WattBridge Energy, LLC |
459 MW | Withdrawn / abandoned |
| Cold Creek Solar Solar · Cold Creek Solar LLC |
455 MW | Withdrawn / abandoned |
| Monarch Creek Wind (B) Onshore wind · EDF Renewables Development, Inc. |
452 MW | Withdrawn / abandoned |
| Dogwood Creek Solar Solar · Dogwood Creek Solar LLC |
432 MW | Withdrawn / abandoned |
| Dogwood Creek Storage Other · Dogwood Creek Solar LLC |
431 MW | Withdrawn / abandoned |
| Gibbons Creek TEERP Coal · TEERP Power Station LLC |
420 MW | Withdrawn / abandoned |
| BRP Rhea BESS Other · BRP Rhea BESS LLC |
414 MW | Withdrawn / abandoned |
| Larisa Solar Solar · ABEI ENERGY & INFRASTRUCTURE LLC |
408 MW | Withdrawn / abandoned |
| Austin Bayou Solar II Solar · Austin Bayou Solar, LLC |
402 MW | Withdrawn / abandoned |
| Firefly Power Battery storage · Firefly Power LLC |
401 MW | Withdrawn / abandoned |
| Plum Creek Solar I Solar · PLUM CREEK SOLAR I, LLC |
400 MW | Withdrawn / abandoned |
| Zapata II W Onshore wind · Nextera |
400 MW | Withdrawn / abandoned |
| Santa Rita Solar Solar · Invenergy |
400 MW | Withdrawn / abandoned |
| Bedias Solar Park Solar · Misae Energy III |
400 MW | Withdrawn / abandoned |
| Spectrum Solar Solar · IP Spectrum, LLC |
400 MW | Withdrawn / abandoned |
| Palacwnd Onshore wind · Palacios Wind, LLC |
367 MW | Withdrawn / abandoned |
| Queue Power Plant Gas · Pro Energy Services LLC |
363 MW | Withdrawn / abandoned |
| Toland Power Plant Gas · ProEnergy Services LLC |
363 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)530 · 95.5 GW
- SPP (Southwest Power Pool)311 · 70.8 GW
- MISO (Midcontinent)70 · 15.9 GW
- West (non-ISO utilities)6 · 2,021 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)