🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Texas, ERCOT

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown53095.5 GW
Active in queue447.2 GW1,976 requests
Agreement signed119.3 GW578 requests
Withdrawn53095.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

530 requests · page 1 of 11
ProjectCapacityStatusLocationRegionQueuedOnline
Corner Solar
Solar · Shannon Solar LLC
1,222 MWWithdrawn / abandoned Crockett, TXERCOT Jun 2019target 2021
R-Cube Wind
Onshore wind · Nextera
1,000 MWWithdrawn / abandoned Denton, TXERCOT Aug 2018target 2020
FGE Texas 1 Gas
Gas · FGE Power
743 MWWithdrawn / abandoned Mitchell, TXERCOT Apr 2013target 2021
Greens Bayou 9 CCGT
Gas · NRG Texas Power LLC
721 MWWithdrawn / abandoned Harris, TXERCOT target 2025
Tehuacana Creek Solar-Alt POI
Solar · Tehuacana Creek Solar LLC
715 MWWithdrawn / abandoned Freestone, TXERCOT Oct 2022target 2025
Hollow Branch Creek Solar SLF
Solar · Hollow Branch Creek Solar LLC
712 MWWithdrawn / abandoned Leon, TXERCOT Dec 2021target 2025
Goldenrod Creek Solar
Solar · Goldenrod Creek Solar LLC
660 MWWithdrawn / abandoned Jackson, TXERCOT Feb 2022target 2025
Bastrop Peaking Generators II
Gas · MPH Bastrop Peakers, LLC
628 MWWithdrawn / abandoned Bastrop, TXERCOT target 2026
Cosmos Solar
Solar · EDF Renewables Development, Inc.
610 MWWithdrawn / abandoned Wharton, TXERCOT Feb 2021target 2024
Old Lunar Solar
Solar · EDF Renewables Development, Inc.
610 MWWithdrawn / abandoned Wharton, TXERCOT Dec 2019target 2029
Scandia Wind DEF
Onshore wind · Scandia Wind LLC
600 MWWithdrawn / abandoned Parmer, TXERCOT Jun 2009target 2020
Apis Solar
Solar · S&S Renewables LLC
534 MWWithdrawn / abandoned Bee, TXERCOT Jul 2023target 2026
Dundee East A Wind Placeholder
Onshore wind · Felix 2, LLC
524 MWWithdrawn / abandoned Baylor, TXERCOT target 2027
OFFERED Combined Cycle Gen
Gas · Blue Cube Operations
520 MWWithdrawn / abandoned Brazoria, TXERCOT Dec 2022target 2025
Bronze Fork Solar
Solar · EDF Renewables Development, Inc.
516 MWWithdrawn / abandoned Haskell, TXERCOT Dec 2019target 2022
Point Mountain Solar
Solar · Hecate Energy
514 MWWithdrawn / abandoned Upton, TXERCOT Apr 2018target 2020
Point Mountain Solar
Solar · Hecate Energy Point Mountain LLC
514 MWWithdrawn / abandoned Crane, TXERCOT Aug 2019target 2024
Brinton Fork Solar
Solar · EDF Renewables Development, Inc.
514 MWWithdrawn / abandoned Haskell, TXERCOT Dec 2019target 2024
Amsterdam Solar II
Solar · Cottonwood Bayou Solar II, LLC
510 MWWithdrawn / abandoned Brazoria, TXERCOT Aug 2021target 2026
Shinnery Hill Solar
Solar · EDF Renewables Development, Inc.
503 MWWithdrawn / abandoned Wichita, TXERCOT Dec 2019target 2025
Green Bird Solar
Solar · Gigawatt Solar LLC
502 MWWithdrawn / abandoned Johnson, TXERCOT Feb 2022target 2024
Dark Lark BESS
Other
500 MWWithdrawn / abandoned Henderson, TXERCOT Jun 2022
Green Valley Wind
Onshore wind · Eon
500 MWWithdrawn / abandoned Val Verde, TXERCOT Feb 2017target 2019
Comanche Run Wind
Onshore wind · Avangrid
500 MWWithdrawn / abandoned Swisher, TXERCOT Mar 2009target 2019
Juno Storage
Other · Intersect Power
495 MWWithdrawn / abandoned Borden, TXERCOT Aug 2018target 2021
ELTEX Power Station
Gas · ELTEX Power Station LLC
488 MWWithdrawn / abandoned Austin, TXERCOT Sep 2024target 2027
Sugarland Power Plant
Gas · ProEnergy Services LLC
484 MWWithdrawn / abandoned Brazoria, TXERCOT Jan 2019target 2021
Halyard Henderson
Gas · Halyard Energy
484 MWWithdrawn / abandoned Henderson, TXERCOT Mar 2014target 2021
Ponta Power Plant
Gas · Pro Energy Services LLC
484 MWWithdrawn / abandoned Cherokee, TXERCOT Dec 2018target 2020
Denver City - Mustang - Gas
Gas · Golden Spread Electric Cooperative, Inc.
472 MWWithdrawn / abandoned Yoakum, TXERCOT Dec 2024target 2029
Deepwater
Gas · AES
462 MWWithdrawn / abandoned Harris, TXERCOT Dec 2017target 2021
Upstream BESS
Battery storage · Upstream Storage LLC
462 MWWithdrawn / abandoned Johnson, TXERCOT Mar 2023target 2026
Ponta Power Station
Gas · WattBridge Energy, LLC
459 MWWithdrawn / abandoned Cherokee, TXERCOT Feb 2021target 2024
Cold Creek Solar
Solar · Cold Creek Solar LLC
455 MWWithdrawn / abandoned Schleicher, TXERCOT Apr 2022target 2026
Monarch Creek Wind (B)
Onshore wind · EDF Renewables Development, Inc.
452 MWWithdrawn / abandoned Haskell, TXERCOT Apr 2019target 2023
Dogwood Creek Solar
Solar · Dogwood Creek Solar LLC
432 MWWithdrawn / abandoned Bastrop, TXERCOT Jun 2022target 2025
Dogwood Creek Storage
Other · Dogwood Creek Solar LLC
431 MWWithdrawn / abandoned Bastrop, TXERCOT Jul 2022target 2025
Gibbons Creek TEERP
Coal · TEERP Power Station LLC
420 MWWithdrawn / abandoned Grimes, TXERCOT Apr 2020target 2020
BRP Rhea BESS
Other · BRP Rhea BESS LLC
414 MWWithdrawn / abandoned Rockwall, TXERCOT Dec 2021target 2024
Larisa Solar
Solar · ABEI ENERGY & INFRASTRUCTURE LLC
408 MWWithdrawn / abandoned Jones, TXERCOT Apr 2019target 2024
Austin Bayou Solar II
Solar · Austin Bayou Solar, LLC
402 MWWithdrawn / abandoned Brazoria, TXERCOT Mar 2024target 2027
Firefly Power
Battery storage · Firefly Power LLC
401 MWWithdrawn / abandoned Tarrant, TXERCOT Feb 2024target 2027
Plum Creek Solar I
Solar · PLUM CREEK SOLAR I, LLC
400 MWWithdrawn / abandoned Grimes, TXERCOT Jun 2020target 2023
Zapata II W
Onshore wind · Nextera
400 MWWithdrawn / abandoned Zapata, TXERCOT Jan 2016target 2019
Santa Rita Solar
Solar · Invenergy
400 MWWithdrawn / abandoned Crockett, TXERCOT Nov 2016target 2022
Bedias Solar Park
Solar · Misae Energy III
400 MWWithdrawn / abandoned Grimes, TXERCOT Oct 2023target 2026
Spectrum Solar
Solar · IP Spectrum, LLC
400 MWWithdrawn / abandoned Comanche, TXERCOT Nov 2018target 2023
Palacwnd
Onshore wind · Palacios Wind, LLC
367 MWWithdrawn / abandoned Matagorda, TXERCOT target 2023
Queue Power Plant
Gas · Pro Energy Services LLC
363 MWWithdrawn / abandoned Galveston, TXERCOT Jan 2019target 2021
Toland Power Plant
Gas · ProEnergy Services LLC
363 MWWithdrawn / abandoned San Patricio, TXERCOT Feb 2019target 2020
Page 1 of 11

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)