United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTTehuacana Creek Solar-Alt POI
Tehuacana Creek Solar-Alt POI is a 715 MW solar request withdrawn in the ERCOT interconnection queue, in Freestone County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2022 (completed)
- Withdrawn / abandonedNov 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 24INR0433
- Grid region
- ERCOT (Texas)
- Developer
- Tehuacana Creek Solar LLC
- Connection point (POI)
- Tap 345kV 46020 Limestone – 68091 Navarro
- Location
- Freestone County, Texas
- Technology
- Solar: 715 MW
- Total requested
- 715 MW
- Study phase
- FIS & SS Incomplete
- Queue status
- Withdrawn
- Entered queue
- 5 October 2022
- Proposed online date
- May 2025
- Withdrawn
- November 2022
Location
Marker shows the centre of Freestone County; the queue data does not give exact sites.
Other requests in Freestone County
- Piedra SolarSolar + storage · 282 MW · agreement signed
- Pin Peaking Energy Center 1 (TEF- Due Diligence)Gas · 228 MW · agreement signed
- Pin Peaking Energy Center 2 (TEF- Due Diligence)Gas · 228 MW · agreement signed
- Bar Candela Solar SLFSolar + storage · 200 MW · agreement signed
- Fairway StorageBattery storage · 120 MW · agreement signed
- Piedra BESSSolar + storage · 104 MW · agreement signed
- Jewett Energy Center 1 GasGas · 1,274 MW · in study
- Silver Dollar SolarSolar + storage · 302 MW · in study
- Amerada SolarSolar + storage · 302 MW · in study
- Simsboro StorageBattery storage · 302 MW · in study
- Douie SolarSolar · 221 MW · in study
- Freestone Battery Storage ProjectBattery storage · 211 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem