OTHER Β· ERCOT

BRP Rhea BESS

BRP Rhea BESS is a 414 MW other request withdrawn in the ERCOT interconnection queue, in Rockwall County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2021 (completed)
  2. Withdrawn / abandonedSep 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
24INR0129
Grid region
ERCOT (Texas)
Developer
BRP Rhea BESS LLC
Connection point (POI)
the 138 kV Royse Switch Substation (#2472; ONCOR)
Location
Rockwall County, Texas
Technology
Other: 414 MW
Total requested
414 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
19 December 2021
Proposed online date
July 2024
Withdrawn
September 2022

Location

Marker shows the centre of Rockwall County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Rockwall County