BATTERY STORAGE · ERCOT

TE Smith Storage

TE Smith Storage is a 125 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Rockwall County, Texas.

Queue statusConsented
  1. PlanningQueued Sep 2021 (completed)
  2. ConsentedNov 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0555
Grid region
ERCOT (Texas)
Developer
BT Smith Storage, LLC
Connection point (POI)
2483 Royse Switch 345kV
Location
Rockwall County, Texas
Technology
Battery: 125 MW
Total requested
125 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
2 September 2021
Agreement signed
8 November 2023
Proposed online date
January 2026

Location

Marker shows the centre of Rockwall County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Rockwall County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem