BATTERY STORAGE · ERCOTTE Smith Storage
TE Smith Storage is a 125 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Rockwall County, Texas.
Queue statusConsented
- PlanningQueued Sep 2021 (completed)
- ConsentedNov 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Jan 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 22INR0555
- Grid region
- ERCOT (Texas)
- Developer
- BT Smith Storage, LLC
- Connection point (POI)
- 2483 Royse Switch 345kV
- Location
- Rockwall County, Texas
- Technology
- Battery: 125 MW
- Total requested
- 125 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 2 September 2021
- Agreement signed
- 8 November 2023
- Proposed online date
- January 2026
Location
Marker shows the centre of Rockwall County; the queue data does not give exact sites.
Other requests in Rockwall County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem