United States βΊ Grid βΊ Interconnection queues βΊ Texas
BATTERY STORAGE Β· ERCOTUpstream BESS
Upstream BESS is a 462 MW battery storage request withdrawn in the ERCOT interconnection queue, in Johnson County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2023 (completed)
- Withdrawn / abandonedApr 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 26INR0106
- Grid region
- ERCOT (Texas)
- Developer
- Upstream Storage LLC
- Connection point (POI)
- 1902 Johnson Switch
- Location
- Johnson County, Texas
- Technology
- Battery: 462 MW
- Total requested
- 462 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 26 March 2023
- Proposed online date
- May 2026
- Withdrawn
- April 2025
Location
Marker shows the centre of Johnson County; the queue data does not give exact sites.
Other requests in Johnson County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem