πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

BATTERY STORAGE Β· ERCOT

Upstream BESS

Upstream BESS is a 462 MW battery storage request withdrawn in the ERCOT interconnection queue, in Johnson County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2023 (completed)
  2. Withdrawn / abandonedApr 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
26INR0106
Grid region
ERCOT (Texas)
Developer
Upstream Storage LLC
Connection point (POI)
1902 Johnson Switch
Location
Johnson County, Texas
Technology
Battery: 462 MW
Total requested
462 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
26 March 2023
Proposed online date
May 2026
Withdrawn
April 2025

Location

Marker shows the centre of Johnson County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Johnson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem