United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTDogwood Creek Solar
Dogwood Creek Solar is a 432 MW solar request withdrawn in the ERCOT interconnection queue, in Bastrop County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2022 (completed)
- Withdrawn / abandonedJan 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 24INR0370
- Grid region
- ERCOT (Texas)
- Developer
- Dogwood Creek Solar LLC
- Connection point (POI)
- tap 345kV 7040 Austrop - 9041 Lost Pines
- Location
- Bastrop County, Texas
- Technology
- Solar: 432 MW
- Total requested
- 432 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 26 June 2022
- Proposed online date
- May 2025
- Withdrawn
- January 2024
Location
Marker shows the centre of Bastrop County; the queue data does not give exact sites.
Other requests in Bastrop County
- Bastrop Peaking Generators (TEF-Due Diligence)Gas Β· 1,104 MW Β· agreement signed
- Big Star SolarSolar Β· 203 MW Β· agreement signed
- Waterloo Solar 1Solar + storage Β· 201 MW Β· agreement signed
- Waterloo BESS 1Solar + storage Β· 106 MW Β· agreement signed
- Big Star StorageBattery storage Β· 80.0 MW Β· agreement signed
- Sim Gideon Combined CycleGas Β· 880 MW Β· in study
- Lost Pines Power ParkGas Β· 880 MW Β· in study
- Fort Worth Power Core Bastrop Gas PlantGas Β· 506 MW Β· in study
- Lund Storage Center 1Battery storage Β· 408 MW Β· in study
- Sim Gideon Gas RiceGas Β· 226 MW Β· in study
- Techne BESSBattery storage Β· 203 MW Β· in study
- Antonio Road BESSBattery storage Β· 156 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem