SOLAR Β· ERCOT

Dogwood Creek Solar

Dogwood Creek Solar is a 432 MW solar request withdrawn in the ERCOT interconnection queue, in Bastrop County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2022 (completed)
  2. Withdrawn / abandonedJan 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
24INR0370
Grid region
ERCOT (Texas)
Developer
Dogwood Creek Solar LLC
Connection point (POI)
tap 345kV 7040 Austrop - 9041 Lost Pines
Location
Bastrop County, Texas
Technology
Solar: 432 MW
Total requested
432 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
26 June 2022
Proposed online date
May 2025
Withdrawn
January 2024

Location

Marker shows the centre of Bastrop County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Bastrop County