United States βΊ Grid βΊ Interconnection queues βΊ Texas
ONSHORE WIND Β· ERCOTR-Cube Wind
R-Cube Wind is a 1,000 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Denton County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2018 (completed)
- Withdrawn / abandonedFeb 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 20INR0160
- Grid region
- ERCOT (Texas)
- Developer
- Nextera
- Connection point (POI)
- 1730 Krum 345kV
- Location
- Denton County, Texas
- Technology
- Wind: 1,000 MW
- Total requested
- 1,000 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 20 August 2018
- Proposed online date
- December 2020
- Withdrawn
- February 2019
Location
Marker shows the centre of Denton County; the queue data does not give exact sites.
Other requests in Denton County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem