United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

ONSHORE WIND Β· ERCOT

R-Cube Wind

R-Cube Wind is a 1,000 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Denton County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2018 (completed)
  2. Withdrawn / abandonedFeb 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
20INR0160
Grid region
ERCOT (Texas)
Developer
Nextera
Connection point (POI)
1730 Krum 345kV
Location
Denton County, Texas
Technology
Wind: 1,000 MW
Total requested
1,000 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
20 August 2018
Proposed online date
December 2020
Withdrawn
February 2019

Location

Marker shows the centre of Denton County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Denton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem