United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Porter Solar

Porter Solar is a 246 MW solar request built and operating in the ERCOT interconnection queue, in Denton County, Texas.

Queue statusOperating
  1. PlanningQueued Jan 2020 (completed)
  2. ConsentedFeb 2022 (completed)
  3. Construction (completed)
  4. OperatingJan 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
21INR0458
Grid region
ERCOT (Texas)
Developer
Porter Solar, LLC
Connection point (POI)
tap 345kv 1429 Jacksboro - 1730 Krum West
Location
Denton County, Texas
Technology
Solar: 246 MW
Total requested
246 MW
Study phase
IA
Queue status
Operational
Entered queue
29 January 2020
Agreement signed
3 February 2022
Proposed online date
July 2024
Came online
January 2025

Location

Marker shows the centre of Denton County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Denton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem