United States › Grid › Interconnection queues › Texas

OTHER · ERCOT

Noble Storage (BESS1)

Noble Storage (BESS1) is a 62.5 MW other request built and operating in the ERCOT interconnection queue, in Denton County, Texas.

Queue statusOperating
  1. PlanningQueued Apr 2022 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingOct 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0598
Grid region
ERCOT (Texas)
Location
Denton County, Texas
Technology
Other: 62.5 MW
Total requested
62.5 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
14 April 2022
Came online
October 2022

Location

Marker shows the centre of Denton County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Denton County