πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OTHER Β· ERCOT

Noble Storage

Noble Storage is a 62.5 MW other request built and operating in the ERCOT interconnection queue, in Denton County, Texas.

Queue statusOperating
  1. PlanningQueued Oct 2020 (completed)
  2. ConsentedOct 2021 (completed)
  3. Construction (completed)
  4. OperatingOct 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0436
Grid region
ERCOT (Texas)
Developer
BT NOBLE SOLAR, LLC
Connection point (POI)
1730 Krum West 345kV
Location
Denton County, Texas
Technology
Other: 62.5 MW
Total requested
62.5 MW
Study phase
IA
Queue status
Operational
Entered queue
22 October 2020
Agreement signed
29 October 2021
Proposed online date
October 2022
Came online
October 2022

Location

Marker shows the centre of Denton County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Denton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem