United States › Grid › Interconnection queues › Texas
GAS · ERCOTBastrop Peaking Generators II
Bastrop Peaking Generators II is a 628 MW gas request withdrawn in the ERCOT interconnection queue, in Bastrop County, Texas.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandonedAug 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 26INR0561
- Grid region
- ERCOT (Texas)
- Developer
- MPH Bastrop Peakers, LLC
- Connection point (POI)
- 7048 Garfield 345kV
- Location
- Bastrop County, Texas
- Technology
- Gas: 628 MW
- Total requested
- 628 MW
- Study phase
- FIS & SS Incomplete
- Queue status
- Withdrawn
- Proposed online date
- May 2026
- Withdrawn
- August 2024
Location
Marker shows the centre of Bastrop County; the queue data does not give exact sites.
Other requests in Bastrop County
- Bastrop Peaking Generators (TEF-Due Diligence)Gas · 1,104 MW · agreement signed
- Big Star SolarSolar · 203 MW · agreement signed
- Waterloo Solar 1Solar + storage · 201 MW · agreement signed
- Waterloo BESS 1Solar + storage · 106 MW · agreement signed
- Big Star StorageBattery storage · 80.0 MW · agreement signed
- Sim Gideon Combined CycleGas · 880 MW · in study
- Lost Pines Power ParkGas · 880 MW · in study
- Fort Worth Power Core Bastrop Gas PlantGas · 506 MW · in study
- Lund Storage Center 1Battery storage · 408 MW · in study
- Sim Gideon Gas RiceGas · 226 MW · in study
- Techne BESSBattery storage · 203 MW · in study
- Antonio Road BESSBattery storage · 156 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem