🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

GAS · ERCOT

Bastrop Peaking Generators II

Bastrop Peaking Generators II is a 628 MW gas request withdrawn in the ERCOT interconnection queue, in Bastrop County, Texas.

Queue statusWithdrawn / abandoned
  1. Planning (completed)
  2. Withdrawn / abandonedAug 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
26INR0561
Grid region
ERCOT (Texas)
Developer
MPH Bastrop Peakers, LLC
Connection point (POI)
7048 Garfield 345kV
Location
Bastrop County, Texas
Technology
Gas: 628 MW
Total requested
628 MW
Study phase
FIS & SS Incomplete
Queue status
Withdrawn
Proposed online date
May 2026
Withdrawn
August 2024

Location

Marker shows the centre of Bastrop County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Bastrop County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem