SOLAR Β· ERCOT

Brinton Fork Solar

Brinton Fork Solar is a 514 MW solar request withdrawn in the ERCOT interconnection queue, in Haskell County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2019 (completed)
  2. Withdrawn / abandonedDec 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
22INR0272
Grid region
ERCOT (Texas)
Developer
EDF Renewables Development, Inc.
Connection point (POI)
60791 Perigee 345kV
Location
Haskell County, Texas
Technology
Solar: 514 MW
Total requested
514 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
16 December 2019
Proposed online date
December 2024
Withdrawn
December 2023

Location

Marker shows the centre of Haskell County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Haskell County