United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Point Mountain Solar

Point Mountain Solar is a 514 MW solar request withdrawn in the ERCOT interconnection queue, in Crane County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2019 (completed)
  2. Withdrawn / abandonedJul 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
22INR0236
Grid region
ERCOT (Texas)
Developer
Hecate Energy Point Mountain LLC
Connection point (POI)
76000 North McCamey 345kV
Location
Crane County, Texas
Technology
Solar: 514 MW
Total requested
514 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
25 August 2019
Proposed online date
December 2024
Withdrawn
July 2022

Location

Marker shows the centre of Crane County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Crane County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem