United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Cattle Drive Solar

Cattle Drive Solar is a 307 MW solar request in interconnection study in the ERCOT interconnection queue, in Crane County, Texas.

Queue statusIn planning
  1. PlanningQueued Jun 2024 (current stage)
  2. ConsentedDec 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
29INR0013
Grid region
ERCOT (Texas)
Developer
NextEra Energy Interconnection Holdings, LLC
Connection point (POI)
76000 North McCamey 345kV
Location
Crane County, Texas
Technology
Solar: 307 MW
Total requested
307 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
13 June 2024
Agreement signed
29 December 2025
Proposed online date
July 2029

Location

Marker shows the centre of Crane County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Crane County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem