United States › Grid › Interconnection queues › Texas

OTHER · ERCOT

Crossett Power Batt

Crossett Power Batt is a 203 MW other request built and operating in the ERCOT interconnection queue, in Crane County, Texas.

Queue statusOperating
  1. PlanningQueued Jun 2020 (completed)
  2. ConsentedAug 2020 (completed)
  3. Construction (completed)
  4. OperatingMay 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
21INR0510
Grid region
ERCOT (Texas)
Developer
Crossett Power Management LLC
Connection point (POI)
76026 Soda Lake 138kV
Location
Crane County, Texas
Technology
Other: 203 MW
Total requested
203 MW
Study phase
IA
Queue status
Operational
Entered queue
2 June 2020
Agreement signed
5 August 2020
Proposed online date
May 2022
Came online
May 2022

Location

Marker shows the centre of Crane County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Crane County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem