SOLAR + STORAGE · ERCOTWestern Flats Storage
Western Flats Storage is a 411 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Crane County, Texas.
Queue statusIn planning
- PlanningQueued Apr 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 26INR0188
- Grid region
- ERCOT (Texas)
- Developer
- Hecate Energy Point Mountain Solar Facility 1 LLC
- Connection point (POI)
- Tap 138 kV 76615 Crane -76635 King Mountain
- Location
- Crane County, Texas
- Technology
- Battery: 411 MW · Battery
- Total requested
- 411 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 9 April 2024
- Proposed online date
- November 2028
Location
Marker shows the centre of Crane County; the queue data does not give exact sites.
Other requests in Crane County
- Soda Lake BESS 1Battery storage · 204 MW · agreement signed
- Soda Lake Solar 2 SLFSolar + storage · 202 MW · agreement signed
- Tri-X Solar 1 SLFSolar + storage · 202 MW · agreement signed
- Western Flats SolarSolar + storage · 410 MW · in study
- Cattle Drive SolarSolar · 307 MW · in study
- Soda Lake BESS 2 SLFSolar + storage · 205 MW · in study
- Tri-X BESS 1 SLFSolar + storage · 205 MW · in study
- BRP Pictor BESSBattery storage · 201 MW · in study
- BRP Ampato BESSBattery storage · 122 MW · in study
- Fowler Ranch StorageBattery storage · 26.1 MW · in study
- Tri-County SolarSolar · 178 MW · suspended
- Crossett Power BattOther · 203 MW · built