Western Flats Solar

Western Flats Solar is a 410 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Crane County, Texas.

Queue statusIn planning
  1. PlanningQueued Apr 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0110
Grid region
ERCOT (Texas)
Developer
Hecate Energy Point Mountain Solar Facility 1 LLC
Connection point (POI)
Tap 138 kV 76615 Crane -76635 King Mountain; POI is 7.85 miles from Crane.
Location
Crane County, Texas
Technology
Solar: 410 MW · Battery
Total requested
410 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
7 April 2023
Proposed online date
November 2028

Location

Marker shows the centre of Crane County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Crane County