United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

GAS Β· ERCOT

Sugarland Power Plant

Sugarland Power Plant is a 484 MW gas request withdrawn in the ERCOT interconnection queue, in Brazoria County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2019 (completed)
  2. Withdrawn / abandonedApr 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
20INR0225
Grid region
ERCOT (Texas)
Developer
ProEnergy Services LLC
Connection point (POI)
44390 Karsten 138kV
Location
Brazoria County, Texas
Technology
Gas: 484 MW
Total requested
484 MW
Study phase
FIS & SS Incomplete
Queue status
Withdrawn
Entered queue
13 January 2019
Proposed online date
June 2021
Withdrawn
April 2019

Location

Marker shows the centre of Brazoria County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Brazoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem