πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Bronze Fork Solar

Bronze Fork Solar is a 516 MW solar request withdrawn in the ERCOT interconnection queue, in Haskell County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2019 (completed)
  2. Withdrawn / abandonedJan 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
22INR0271
Grid region
ERCOT (Texas)
Developer
EDF Renewables Development, Inc.
Connection point (POI)
Tap 345kV 60515 Clear Crossing - 1421 Willow Creek
Location
Haskell County, Texas
Technology
Solar: 516 MW
Total requested
516 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
16 December 2019
Proposed online date
December 2022
Withdrawn
January 2022

Location

Marker shows the centre of Haskell County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Haskell County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem