United States › Grid › Interconnection queues › Virginia
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in Virginia — page 4
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Fiddlers Ridge Wind Facility Onshore wind |
63.3 MW | Agreement signed |
| Battery storage project AH2-072, Washington County Battery storage |
62.1 MW | In study |
| Cerulean Solar and Mulberry BESS Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
62.0 MW | In study |
| Battery storage project AG2-384, Chesterfield County Battery storage · Virginia Electric and Power Company |
60.8 MW | In study |
| Moon Corner Solar Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
60.0 MW | In study |
| Solar project AG2-171, Lunenburg County Solar · Couch Creek Solar LLC |
60.0 MW | In study |
| Cricket Solar Solar |
60.0 MW | Agreement signed |
| Battery storage project AH2-032, Prince William County Battery storage |
60.0 MW | In study |
| Battery storage project AH2-033, Prince William County Battery storage |
60.0 MW | In study |
| Battery storage project AI2-231A, Botetourt County Battery storage |
60.0 MW | In study |
| Pigeon Run Solar and Storage Solar · Pigeon Run Solar, LLC |
60.0 MW | Agreement signed |
| Solar project AI1-123, Lunenburg County Solar |
59.0 MW | In study |
| Battery storage project AG2-272, Pittsylvania County Battery storage · Tupelo Storage, LLC |
55.0 MW | In study |
| Solar project AI2-224, Charlotte County Solar |
55.0 MW | In study |
| Battery storage project AH2-061, Prince William County Battery storage |
55.0 MW | In study |
| Battery storage project AH2-060, Prince William County Battery storage |
55.0 MW | In study |
| Gladys Solar Solar · Gladys Solar, LLC |
53.0 MW | Agreement signed |
| Solar project AH2-080, Brunswick County Solar |
52.7 MW | In study |
| Battery storage project AH2-145, King George County Battery storage |
52.3 MW | In study |
| Wythe County Solar Project Battery storage |
52.2 MW | Agreement signed |
| Solar project AH1-227, Wise County Solar · Virginia Electric and Power Company |
51.3 MW | In study |
| Knoxville Solar Solar |
51.0 MW | Agreement signed |
| Solar project AI2-244, Nottoway County Solar |
50.3 MW | In study |
| Battery storage project AJ1-001, Mecklenburg County Battery storage |
50.0 MW | In study |
| Battery storage project AI2-042, Louisa County Battery storage |
50.0 MW | In study |
| Amherst Solar Solar |
50.0 MW | Agreement signed |
| Tavern Energy LLC Battery storage · Tavern Energy, LLC |
50.0 MW | In study |
| Beckett Solar Solar |
50.0 MW | Agreement signed |
| Walnut Solar I Solar |
50.0 MW | Agreement signed |
| Greenwood Solar Solar |
50.0 MW | Agreement signed |
| Solar project AI2-416, Augusta County Solar |
50.0 MW | In study |
| Battery storage project AI1-088, Prince George County Battery storage |
50.0 MW | In study |
| Battery storage project AH1-269, Pulaski County Battery storage · Claytor Energy Storage, LLC |
50.0 MW | In study |
| Battery storage project AI1-086, Greensville County Battery storage |
50.0 MW | In study |
| Henry County Solar Facility Solar |
50.0 MW | Agreement signed |
| Battery storage project AG2-341, Mecklenburg County Battery storage · Mighty Blue LLC |
50.0 MW | In study |
| Dulles Solar and BESS Battery storage |
50.0 MW | Agreement signed |
| Battery storage project AI1-087, Prince George County Battery storage |
50.0 MW | In study |
| Sunridge Solar Solar |
50.0 MW | Agreement signed |
| Solar project AJ1-022, Mecklenburg County Solar |
49.0 MW | In study |
| Switchgrass Solar 1 Solar |
49.0 MW | Paused / redesign |
| Solar project AI1-011, Cumberland County Solar |
46.0 MW | In study |
| Battery storage project AH2-241, City Of Chesapeake County Battery storage |
45.0 MW | In study |
| Waller Solar I Solar |
45.0 MW | Agreement signed |
| Battery storage project AI2-277, Greensville County Battery storage |
45.0 MW | In study |
| Waller Solar I Solar |
45.0 MW | Agreement signed |
| Amelia Energy Facility Solar · Amelia Energy Facility, LLC |
41.0 MW | In study |
| Solar project AI2-079, Fauquier County Solar |
40.7 MW | In study |
| Ho-Fel Solar Solar |
40.0 MW | Paused / redesign |
| Solar + storage project AH1-098, Carroll County Solar + storage · Pine Branch Solar, LLC |
40.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)